Gazstroy Brickworks produces clinker bricks for fair-faced brickwork and large-size clay blocksPart 1: Line A for large-size clay blocks filled with mineral wool

The brickworks built and commissioned by Lingl in 2011 for the company OOO“Gazstroy” is one of the largest in the territory of the Russian Federation. The plant in Rjabovo, around 75 km southeast of St. Petersburg, consists of two completely independent production lines for the production of clinker bricks for fair-faced brickwork and large-size clay bricks, which can also be filled.

1 Introduction

The entire production plant was erected by German suppliers. Lingl was responsible for installation of the main part of the production plant, starting from the cutters to the packaging systems. Installation of the comprehensive equipment was started in August 2010 and the acceptance runs of the two production lines were performed in October and November 2011.

The dimensions of the “double plant” are impressive: the complete Lingl technology for the two production lines is installed in one building with a length of 180 m and a width of 140 m.

On account of the uniqueness of...

Related articles:

Issue 2013-05

Lingl supplies new-generation technology to Briqueteries de Ploegsteert

The Belgian brick manufacturing company Briqueteries de Ploegsteert has equipped its factory with a Turbo II Modular Grinding Center and a Coriso Filling Installation supplied by Lingl. Ploegsteert...

more
Issue 2011-6

New orders for Lingl

Major order from Ziegelwerk Klosterbeuren Following intensive planning Lingl has received an order for the supply of a complete grinding and filling installation from Ziegelwerk Klosterbeuren. This...

more
Issue 2011-11 Exclusive cooperation in brick filling installations

Grenzebach and Lingl agree on know-how cooperation

Grenzebach and Lingl have entered into cooperation in brick filling installations. From now on both partners will jointly offer the technological systems for filling wall bricks with small cubes of...

more
Issue 2012-1-2

Otto Staudacher Brickworks starts operation of second brick filling installation

Staudacher Brickworks in Balzhausen, part of the Thermopor Group, has responded early to the growing requirements for the thermal insulation of residential buildings. Its second latest generation...

more
Sustainable wall building materials on the advance

Every second Poroton exterior wall clay block now filled

In 2012 the members of Deutsche Poroton that manufacture clay blocks were able to increase the percentage of filled clay blocks to 16% (2.3 mill. m3) of the total sales of the Association. In the...

more