Using alternative fuels in a Moroccan brickworks in a CDM project

An ongoing “Clean Development Mechanism” (CDM) project in Morocco is presented; this project is being realized at the brickworks Societé Briqueterie Bati Chouia S.A. (SBBC), around 30 km south of Casablanca. Goal of the project is to improve the company’s ­sustainability and profitability and enable investment in new technologies.

1 Introduction

In the scope of the Kyoto Protocol [1], the industrial nations were given the option to realize “Clean Development Mechanism” (CDM) projects in the developing and threshold countries cited in Annex B of the Kyoto Protocol, in order to achieve their contractually agreed emission reduction goals. For these countries, no emission reduction goals are agreed, although they have signed the Kyoto Protocol. The reduction is undertaken on a voluntary basis. For this reduction, in the scope of a CDM project, “Certified Emission Reductions” (CERs) can be issued. These can be freely traded...

Related articles:

Issue 2012-05

Carbon footprinting and emission reductions in the brick industry – Case study CDM project SBBC Morocco

SBBC Societé Briqueterie Bati Chaouia is one of the biggest brickworks in Morocco. Beginning in 2008, both energy efficiency and fuel switch measures were technically implemented in the production...

more
Issue 2012-7-8

Bernini Impianti with focus on burners for alternative energies

The Italian specialist for burner equipment has developed a new burner for alternative fuels on the basis of biomass, e.g. waste from the utilization of sunflowers. This has already been installed at...

more

Hörl & Hartmann Brickworks switch entire production to natural gas

Hörl & Hartmann Brickworks (Dachau, Gerst-hofen) have switched all production sites to operation with natural gas. This conversion is reducing fuel-related emissions by around 20% and is the latest...

more
Issue 2011-4

Sabo supplies production plant for Ideal Brique, Tunisia

The new projects of the plant engineering company Sabo in Tunisia include a brickworks with a daily capacity of 800 t for its client Ideal Brique. The project has been designed to allow an increase...

more
Issue 2016-5

Beralmar supplies new hot air generation system to Morocco

T?he Spanish company Beralmar has supplied a new system for the generation of clean hot air with biomass firing for the Moroccan brickworks Briqueterie Midibriq, Tangiers. A CSD/1500 direct flame...

more