Direxa and Incerpaz inaugurate “Ceramica Estructural”

In 2013 Direxa Engineering installed a modern brick plant for the Incerpaz Group in Santa Cruz de la Sierra, Bolivia. “Ceramica Estructural” is the first fully automatic production line for the Incerpaz Group, a Bolivian market leader in masonry bricks and roofing tiles.

The automatic brick plant is the result of the good cooperation between Incerpaz and Direxa. The project minimized transport costs and import taxes as Direxa had trained the local suppliers in Bolivia and Brazil so that they could manufacture most of the equipment and structures needed.

Ceramica Estructural produces 400 t per day of bricks and structural blocks. The complete production line was installed in a single building measuring 30 m x 180 m and includes everything from preparation, through extrusion, drying and firing to palletizing.

For this project, Direxa choose the “Chinook balancelle” dryer. This drying process allows continuous ventilation and rapid drying in just three hours. The “Chinook” also allows easy automation, and a compact layout.

The installed kiln is a Direxa perfectly sealed kiln with a steel structure. This allows firing with high pressure and homogeneity, enabling outstanding product quality and low energy consumption. The PCCER program automatically monitors drying and firing. It controls the burners and air flows.

Loading and unloading of the dryer are automatic. The kiln car setter uses a robot. To facilitate palletizing and automation, packs measuring 1200 x 1200 mm were chosen. An unloading gripper palletizes the products.

Ceramica Estructural data

› Production: 400 t/day
› Fuel: gas
› Chinook dryer: 6 m x 80 m
› Kiln: 4 m internal x 130 m
› Building: 30 m x 180 m
x

Related articles:

Issue 2012-09

Direxa Engineering develops castable kiln for Cerâmica City in Brazil

Cerâmica City entrusted Direxa Engineering, LLC with the engineering, supervision and commissioning of a kiln to produce 400 t structural blocks and related products. This project was the first for...

more
Issue 2013-09

Direxa Engineering successfully concludes projects

General Shale (­Wienerberger) Rome plant – coal-to-gas ­conversion for kiln With the price of gas having dipped down dramatically in the USA over the last few years, General Shale has recently...

more
Issue 2014-07

De Boer Machines supplies two kiln car cleaners to the United Kingdom

Earlier this year, De Boer Machines Nederland BV installed a dedicated kiln car cleaner at Carlton Brick in Grimethorpe, Barnsley in the UK. Since De Boer took over the activities of GSP from...

more
Issue 2011-12

New Sacmi kiln for El Aguila for the production of 60 000 clay roofing tiles per day

Sacmi Heavy Clay has concluded a major supply contract with the leading Mexican clay brick and tile maker, El Aguila. Sacmi has already supplied one innovative 120-m-long roller kiln with a width of...

more
Issue 2015-05

Sabo S.A. working successfully on the Latercer SAC project in Peru

Work on a modern, automated tunnel kiln for Latercer SAC, Lima, Peru, is progressing swiftly. The kiln designed for a production capacity of 500 t fired product per day is being built according to a...

more